1 29/12/2014 Kharafi National KSC Construction, Erection, Assembly, Installation, Termination, Testing and Commissioning of LV Electrical Power System, Cable Pulling and Cable Trays Including Equipment Works. 074300/B/017 Installation
2 28/04/2015 National Contracting Company MEW Contracts for Substation & Cable Feeders, Installation of 132 kV Cable Terminations and HV Testing. NCC/MEW/ESCGTC/0415 Cable Division / Jointing
3 02/06/2015 AC DC General Trading & Contracting Company HV AC Test and Electrical Site Tests for 400 kV Cable Feeders. ACDC/465/2015 Cable Division / Testing
4 09/11/2015 Prysmian Group Assembly & Installation works for 132 kV, 1C XLPE Cable for Jaber Al Ahmed Project. MEW/C/4846-2014/2015 Cable Division Installation / Testing
5 09/11/2015 Prysmian Group Assembly & Installation works for 132 kV & 33 kV, 1C XLPE & oil filled Cable for Jamal Abdul Nasser Street Project. Jamal Abdul Nasser Street Project Cable division Installation / Testing
6 15/01/2016 ABB Kuwait Testing & Commissioning of 300/132/33/11 kV Substation at Rawdatein ABB/MEW/T&C/015 Sub Station Testing & Commissioning
7 21/01/2016 ABB Kuwait Maintenance of Substations at various locations at Kuwait ABB/MEW/T&C/32 Sub Station Testing & Commissioning